Isolated connection to the building structure using four threaded vertical rods and horizontal cable restraints

Equipment may have pre-installed brackets for angle support attachments. See Figure 107 and Figure 108.

Figure 107: Plan view of vibration isolation suspended attachment to the building structure.

Side view shows vibration isolators, rods (without rod stiffeners), and cables.

Figure 108: Side view of vibration isolation suspended attachment to the building structure.

Step 1: Attach the equipment to the building structure using threaded rods, isolators and anchors

For the isolator detail, see Figure 109. For building structure attachment details, see Figures 95 to 100.

Figure 109: Isolator detail.

Step 2: Attach anchors and cable to the building structure

For details on anchorage and cable connection to the building structure, see Figure 102

Step 3: Attach cables to equipment

For cable assembly, see Cables. For cable attachment to equipment, see Figure 110

Figure 110: Attachment of cable/rod assembly to the equipment.