You require 70% or better to pass this quiz.
Quizzes can be repeated until a passing score is achieved.
0 of 20 Questions completed
Questions:
You have already completed the quiz before. Hence you can not start it again.
Quiz is loading…
You must sign in or sign up to start the quiz.
You must first complete the following:
0 of 20 Questions answered correctly
Your time:
Time has elapsed
You have reached 0 of 0 point(s), (0)
Earned Point(s): 0 of 0, (0)
0 Essay(s) Pending (Possible Point(s): 0)
1. What does commissioning of mechanical systems really mean?
The commissioning process (often referred to as “acceptance testing”) includes achieving, verifying, testing, accepting, and documenting that the performance of mechanical systems meets design intent and the owner and occupant needs.
2. What is the purpose of mechanical systems commissioning?
The purpose of mechanical systems commissioning is to increase the reliability of mechanical systems after installation by identifying problems and providing a set of baseline values for comparison with subsequent routine tests.
3. What is the typical cost of commissioning a mechanical system on a new building?

4. What are the typical cost savings of commissioned versus non- commissioned facilities for energy savings?
Cost savings resulting from commissioned versus non-commissioned facilities for energy savings are reported from 8 to 50 percent with average savings of about $.75 per square foot.
5. Which phase of a commissioning plan are the actual tests performed?
Design Phase is the develop of the pre-functional test plan and include a pre-functional test procedure for each system using the criteria established above.
6. Water flow through a boiler or chiller is maintained at a ______ rate.
Water flow through the boiler and chiller are maintained at a constant rate with a three- way control valve.
7. True or False? Fluid flow in coils or air flow through the AHU can be adjusted for interior environmental control.
Fluid flow in coils or air flow through the AHU can be adjusted for interior environmental control.
8. _______ dampers are dampers which close when a fuseable link melts and permits the damper to close.
Fire dampers are dampers which close when a fuseable link melts and permits the damper to close.
9. In troubleshooting a vibrating ventilation fan, which of the following doesn’t need to be checked?
You are to check the power supply
10. As part of the commissioning effort each component should be checked for ______ by a procedure using inspections and tests as defined by the specific equipment manufacturers.
All of the above
11. What type of air compressor would warrant use on a large system up to 18,000 CFM?
Centrifugal compressors are used in large systems up to 18,000 cfm.
12. What component of an air compressor system is being diagnosed if checking safeties and interlocks to the fire protection system?
The General controls
13. What is the normally the temperature at which fixed temperature detectors are activated in common areas?
Fixed temperature detectors are activated when the sensor inside the detector reaches a set temperature. This temperature is normally 135°F for common areas.
14. A wet pipe sprinkler system does not flow during tests, what should be checked?
You check the shut off valves
15. True or False? Lifting devices are NOT part of commissioning mechanical systems.
Lifting devices are part of commissioning mechanical systems.
16. Name at least one test device required for elevator inspection?
Voltmeter
17. What critical component separates the water supply from the process and potable water?
The water supply to a facility normally meets potable (drinking) water standards. The water supply is separated from facility potable water with a back-flow preventer and from the facility process water with a second back flow preventer.
18. If the water supply and treatment system has poor water quality, what should be checked?
Correct chemicals and correct quantity of chemicals added
19. Which of the following systems are NOT part of the commissioning process?
None of the above
20. True or False? Upon achieving final acceptance at the conclusion of the post acceptance period, the last step of the commissioning process, the owner and/or his operating and maintenance (O & M) contractor take over full ownership and responsibility of the mechanical systems.
Upon achieving final acceptance at the conclusion of the post acceptance period, the last step of the commissioning process, the owner and/or his operating and maintenance (O & M) contractor take over full ownership and responsibility of the mechanical systems.